Practice on 2024 LATEST PSK-I Exam Updated 140 Questions
Download Latest PSK-I Dumps with Authentic Real Exam QA's
NEW QUESTION # 44
To effectively track Work in Progress (WIP), a team should clearly define what it means to have 'started' work and to have 'finished' work. This will typically be included in the Scrum Team's definition of "Workflow" policy.
How are these various points of flow defined? (choose the best answer)
- A. However the Scrum Team decides to define it. The definition must be in agreement with the Developers and the Product Owner.
- B. Each point of flow is assigned an owner and will be defined by that owner.
- C. However the Developers choose to define it. They have the final say on managing the Sprint Backlog.
- D. Product Backlog items that conform with the team's Definition of Ready are considered WIP.
- E. Any Product Backlog item in the Sprint Backlog that is not 'done' is considered WIP.
Answer: A
NEW QUESTION # 45
True or False: The primary purpose of measuring Work Item Age is to identify bottlenecks in the workflow that will need to be addressed.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 46
True or False: Work Item Age is a leading indicator for the length of the Scrum Team's feedback loop for that (in progress) item.
- A. True
- B. False
Answer: A
NEW QUESTION # 47
A Scrum Team has a Service Level Expectations (SLE) of 85% work items completed in eight days or less.
What is the likelihood of a work item to meet the 8-day SLE cycle if it has just surpassed the 50th percentile workflow stage? (choose the best answer)
- A. Nothing changes. The level of confidence to meet the SLE remains at 85%.
- B. The likelihood of meeting the team's SLE increases.
- C. The likelihood of meeting the team's SLE decreases.
- D. The level of confidence to finish the item cannot be forecasted at this point.
Answer: A
NEW QUESTION # 48
Sprint Planning mainly leverages Throughput in order to create a forecast for the Sprint Backlog.
Which metric would be most relevant to inspect, during Sprint Planning, if you have some items left over from the previous Sprint?
- A. Cycle Time.
- B. Work in Progress.
- C. Story Points.
- D. Work Item Age.
- E. Lead Time.
Answer: B
NEW QUESTION # 49
Little's Law is extremely valuable for directly predicting the future since it gives us a measure of what happened in the past? (Choose the best answer)
- A. True - By understanding our Cycle Time we can use Little's Law to reduce our WIP limits.
- B. False - Relying only on your Cycle Time measurements may incorrectly influence you to cut your WIP limits.
Answer: B
NEW QUESTION # 50
Which of the following will help a Scrum Team achieve flow optimization? (choose the best 4 answers)
- A. Padding estimates to allow space in the Sprint Backlog.
- B. Visualization of the workflow
- C. Limiting WIP.
- D. Inspecting and adapting their definition of "Workflow".
- E. Active management of work items in progress.
Answer: B,C,D,E
NEW QUESTION # 51
True or False: Kanban can be used to help improve the flow of the Sprint. It can also be used to help improve the flow of work in/out of the Sprint. Regardless, the Kanban Definition of Workflow is owned by the Developers.
- A. False
- B. True
Answer: A
NEW QUESTION # 52
True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.
- A. True
- B. False
Answer: A
NEW QUESTION # 53
Which of the following is true if the Developers allocate a percentage of their capacity for unplanned work during the Sprint Planning? (choose the best answer)
- A. The value of the Sprint Goal decreases as less work is dedicated to the objective.
- B. The Sprint Goal becomes more important. It can help the Developers their focus as new Product Backlog items are pulled into their Sprint Backlog.
- C. Reserving capacity for unplanned work should not be allowed as it introduces risks of failing to deliver on their commitment.
Answer: B
NEW QUESTION # 54
Who is accountable for managing the Kanban board in the Sprint Backlog? (Choose the best answer)
- A. The Scrum Team
- B. The Scrum Master
- C. The Developers
- D. The Product Owner
Answer: C
NEW QUESTION # 55
True or False: A Scrum Team's workflow is the team's "policy" for how items move through different states towards 'done'.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 56
Which is the LEAST accurate description of Cycle Time? (choose the best answer)
- A. The total amount of time an item is in a state/column.
- B. The length of time from starting work on the item to when it is finished.
- C. The quantity/number of items that are delivered within a specified period of time.
- D. The length of time a work item takes from idea stage to feedback from users after release to production.
Answer: C
NEW QUESTION # 57
Scrum Teams using Kanban need to track which four metrics of flow? (choose the best answer)
- A. Throughput, Work in Progress (WIP), Velocity, Lead Time.
- B. Work in Progress (WIP), Work Item Age, Throughput, Cycle Time.
- C. Work in Progress (WIP), Velocity, Lead Time, Cycle Time.
- D. Velocity, Lead Time, Cycle Time, Cost.
Answer: B
NEW QUESTION # 58
The Cumulative Flow Diagram is most helpful in visualizing which of the following two metrics? (choose the best two answer)
- A. Throughput.
- B. Work in Progress (WIP) trends.
- C. Where active items are in the workflow and the typical cycle times for the team.
- D. Cycle Time trends and distributions.
Answer: A,B
NEW QUESTION # 59
Which of these metrics is most valuable for Sprint Planning? (Choose the best answer)
- A. Throughput.
- B. Points Delivered.
- C. Cycle time.
- D. Work Item Age.
Answer: A
NEW QUESTION # 60
Which is the most appropriate metric to look at if you want to determine when an item that has already started is going to finish?
- A. Cycle Time.
- B. Team Capacity.
- C. Work Item Age.
- D. Team Velocity.
- E. Lead Time.
Answer: C
NEW QUESTION # 61
True or False: Kanban is a strategy that complements the Scrum framework with a pull system. The Scrum framework by itself also contains elements of a pull system.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 62
True or False: The Scrum Master is responsible for setting the WIP Limits.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 63
The Work in Progress (WIP) Limit can change: (choose the best answer)
- A. only at the Sprint Planning.
- B. only at the Daily Scrum.
- C. only at the Sprint Retrospective.
- D. when Product Owner chooses.
- E. at any time.
- F. Changes should not occur once WIP Limits are created.
Answer: E
NEW QUESTION # 64
Why aren't feedback loop practices included in the Kanban Guide for Scrum Teams? (choose the best answer)
- A. Kanban boards are the only feedback loops needed for Scrum Teams using Kanban.
- B. A Scrum Team self-manages and decides what feedback loops are necessary to include in their workflow.
- C. Kanban does not require feedback loops as it focuses on improving productivity. Feedback loops only apply when using Scrumban.
- D. The Kanban Guide for Scrum Teams builds upon the Scrum Guide. There is no need to explicitly add feedback loop practices as they are already in Scrum.
Answer: D
NEW QUESTION # 65
Is the Scrum Master role needed for Scrum Teams using Kanban? (choose the best answer)
- A. YES
- B. NO
- C. IT DEPENDS
Answer: A
NEW QUESTION # 66
True or False: Scrum Teams using Kanban can release anytime during a Sprint as well as multiple times during the Sprint.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 67
......
Scrum PSK-I certification exam is designed to assess the knowledge and skills of Scrum practitioners who wish to work with Scrum and Kanban together. Kanban is a visual process management system that helps teams visualize and optimize their workflows. Professional Scrum with Kanban level I certification exam covers topics related to Scrum and Kanban, including the principles, frameworks, roles, events, and artifacts of Scrum, as well as the principles and practices of Kanban.